BASSRA WASTE WATER TREATMENT PLAN
by editor | May 5, 2026 | 0 comments
Bassra
Wastewater
Treatment Plant
Cairo - Egypt
📄
Similar Contract No.
2022/2021-20
🏭
Contract Identification
Bassra Wastewater Treatment Plant - Hayah Kareema
📅
Award Date, Implementation Period
2022
✅
Actual Completion Date
March 2023
👷
Role in Contract
Main Contractor ✓
Subcontractor
Management Contractor
💰
Total Contract Amount
340,000 USD
👥
If Partner in a JV, or Subcontractor, Specify Participation in Total Contract Amount
N/A
N/A
N/A
🏛️
Employer's Name
Hayah Kareema Foundation
📍
Address
Second District - New Cairo
☎️
Telephone / Fax Number
16711
✉️
info@arabcont.com
📋
Description of the Similarity
The scope of work includes, but is not limited to:
- Extensive excavation and back-filling operations.
- Supply and back-filling of clean replacement soil.
- Mechanical excavation for foundation works.
🪙
Amount
Excavation and Backfilling Works:
- Total Cost USD 236,593.
Mechanical Excavation:
- Total Cost USD 17,000.
Site Cleaning:
- Total Cost USD 68,000.
📐
Physical Size
- Excavation: 158,400 m³.
- Back-filling Works: 57,516 m³.
- Mechanical Excavation Works: 19,325 m³.
🛡️
Complexity
- Diverse scope and extensive earthworks with varying conditions.
- Tight schedule.
⚙️
Methods
- Use of equipment and manual labor for back-filling on layers.
- Mechanical excavation for foundation works.