AL – ATTIYAT AL – BAHARIYA WASTE WATER

by editor | May 5, 2026 | 0 comments
AL – ATTIYAT AL – BAHARIYA WASTE WATER

Al-Attiyat
Al-Bahariya
Wastewater

Cairo - Egypt
📄

Similar Contract No.

2022/2021-18

🏭

Contract Identification

Al-Attiyat Al-Bahariya Wastewater Treatment Plant in Abnoub - Hayah Kareema

📅

Award Date, Implementation Period

August 2021, 3 months

Completion Date

April 2024

👷

Role in Contract

Main Contractor

Subcontractor

Management Contractor

💰

Total Contract Amount

318,257 USD

👥

If Partner in a JV, or Subcontractor, Specify Participation in Total Contract Amount

N/A

N/A

N/A

🏛️

Employer's Name

Hayah Kareema Foundation

📍

Address

Second District - New Cairo

☎️

Telephone / Fax Number

16711

✉️

E-mail

partners.communication@hayakarima.com

🏗️

Principal Contractor

The Arab Contractors - Osman Ahmed Osman & Co

43 Adly St., Cairo

02 23938050

info@arabcont.com

📋

Description of the Similarity

The scope of work includes, but is not limited to:

  • Extensive excavation and back-filling operations.
  • Supply and back-filling of clean replacement soil.
  • Construction of cement block structures.
  • Mechanical excavation for foundation works.
  • Feeding the concrete mixer with sand and gravel.
🪙

Amount

Excavation Works:

  • Total Cost USD 308,674.

Feeding the Concrete Mixer with Sand and Gravel:

  • Total Cost USD 9,583.
📐

Physical Size

  • Excavation and Back-filling Works: 179,682 m³.
  • Mechanical Excavation Works: 9,396 m³.
  • Feeding the concrete mixer with sand and gravel: 18,687 m³.
  • Supplying and building of cement block structures: 744 m³.
🛡️

Complexity

  • Diverse scope and extensive earthworks with varying conditions.
  • Tight schedule.
⚙️

Methods

  • Use of equipment and manual labor for back-filling on layers.
  • Mechanical excavation for foundation works.