DESIGN AND IMPLEMENTATION OF THREE WATER WELLS HADIBO
by editor | May 5, 2026 | 0 comments
Design and Implementation of
Three Water Wells
Hadibo
Socotra - Yemen
Contract Identification
Design and Implementation of Three Water Wells, Hadibo - Socotra / Yemen
Award Date, Implementation Period
May 2018, 12 months
Completion Date
May 2019
Role in Contract
Main Contractor
Subcontractor
Management Contractor
Total Contract Amount
USD 495,135
Four hundred ninety-five thousand and one hundred thirty-five dollars
If Partner in a JV, or Subcontractor, Specify Participation in Total Contract Amount
N/A
N/A
N/A
Employer's Name
Saudi Program for the Reconstruction & Development of Yemen
Address
https://www.facebook.com/SaudiDRPY/
Description of the Similarity
Prepare all surveys, studies, design, and required project documents.
Water:- Drilling of the four wells.
- Supply and installation of two pumps.
- Supply and installation of pipes for water conveyance inside the pump station.
- Works included related ancillary elements such as valves, chambers, and meters.
- Construction of boundary walls for each well.
- Construction of operator rooms.
- Construction of electricity generator rooms.
- Quality control activities.
Amount
Water:
- The total cost of the water network works is USD 89,800.
Built Environment:
- Construction cost of the boundary walls is USD 16,200.
- Buildings: USD 32,100.
Physical Size
Water:- The four wells are of dimensions 25 m², depth 15 m, and net length 16 m.
- The walls are of height 1.9 m and length 1.2 m for each.
- The operator rooms are of area 18 m².
- The electricity generator rooms are of area 16 m².
- The two pumps are featured with 120 m head and 25 m³/hour flow each.
- The pipes are of diameter 3 inch and 60 m length for water conveyance inside the pump station.
Complexity
- High surface water level, which led to continuous water drainage.
- Poor soil type, which required soil reinforcement during excavation.
- The well was deep, requiring equipment and personnel to be sent down without affecting the project timeline.
- The initial pipeline design interrupted lands that required expropriation, so the horizontal and vertical pipeline was redesigned.
- Adverse weather conditions occurred during the rain season in Socotra from May to October.
- Ships do not enter the island for five months.
Methods / Technology
- Used the traditional method.
- Used heavy equipment in drilling.
- Working hours were arranged in three shifts.
- Used suction pumps to remove surface water.
Other Characteristics
N/A